2019 LED Streetlight Retrofit Project

Current Phase Progress as of April 9, 2019.

Phase I: February to March 2019

Phase I Residential Streets fixtures (2,000) have all been completed. Minor Arterial Streets in Phase I (Date, Margarita, Whitewood, Alta Murrieta, etc) will be completed by April 19, 2019. Major Arterial Streets (Winchester Road, Murrieta Hot Springs) will be scheduled for overnight work.

Phase II: April 2019

  • Scope: Retrofit of 1,364 Residential Street and Major Arterial Fixtures
  • LED Fixture Specs: Residential Streets: 14 watt, 2700k Color Temp, 1,900 Lumen
  • Arterial Streets: 84 watt, 2700k Color Temp, 8,500 Lumen

To minimize impact to traffic, Major Arterial streets will be scheduled for overnight work.

  • Working Hours: Monday through Friday, 7:30 a.m. to 4:30 p.m.
  • Contractor: Siemens Mobility
  • Project Manager for City: Brian Crawford
    Email Brian Crawford (please allow 3 business days for a reply, if required)

Notes

  • Contractor has been instructed to avoid areas around schools during drop-off and pick-up times.
  • No work will be done while raining since it would pose a hazardous condition to contractor crews.
  • Overall schedule dependent on weather conditions.
  • Some major arterial streets are scheduled for overnight retrofit (i.e.- Murrieta Hot Springs Road, Cal Oaks).
Murrieta Streetlight LED Retrofit Project Map